What the standard asks
Section 1 of the 2026 Electronics standard, Work organization and management, is worth 5% of the marks (WorldSkills Occupational Standards, Electronics, WorldSkills Shanghai 2026, checked 2026-11-25). It asks you to plan your work so you finish on time with the parts and tools you have, to change the order of your work when a problem comes, and to check and improve your own methods.
The section page gives a simple split for a three-hour module and says to write checkpoints. This lesson shows how to build the plan from evidence instead of hope: read the task into deliverables, estimate each job from your own log, order the jobs by what depends on what, and set checkpoints you can prove with a meter. Then it shows the logbook that makes next week's plan better than this week's.
The 5% is small. The plan protects the other 95%.
The theory
Read the task into deliverables
Read the whole task once for the picture. Then read it again with a pen. Every time the task asks for something that will be marked or handed in, give it a number. We call each one a deliverable.
- Look for the verbs: fit, build, measure, record, program, draw, hand in.
- Copy every number with its limit: "3.3 V ±2%", "update every second", "A4, one page".
- Write the hand-in list: the board, which files, with which names, in which folder, and which printed pages. A file saved in the wrong place can cost the same as a fault.
- Anything unclear goes on a separate list of questions for the Expert. The lesson on talking to an Expert or a client shows how to ask them.
Our three-hour practice modules turn into 15 to 30 deliverables each. Count yours. If you count fewer than the task's own numbered items, you skipped something.
Plan from your log, not your best day
Your logbook holds your real times for each kind of job. Plan with the time you beat in 8 runs out of 10. We call it your 80% time. Sort your last ten times for a job and take the eighth.
Your best time is a trap. You reached it once, on a good day, with no fault. Plan with it and you will be late nine times in ten.
If you have no log yet, guess, write "guess" beside the number, and start logging today.
Keep about 10% of the module unplanned: 18 minutes in three hours. Something always takes longer.
Order the jobs by what depends on what
Some jobs block others. You cannot test the microcontroller until the supply works. You cannot fill the results table until you have measured. Draw the chain before you start.
Four rules come out of it:
- Power first, and prove it. Fit the supply block, then measure it before you fit an expensive chip. A wrong regulator or a reversed capacitor found now costs 5 minutes. Found later, it can cost the chip.
- Build a block, test a block. A fault in one small block is quick to find. A fault somewhere on a full board is not.
- Write as you go. Put each measurement in the table the moment you take it, with its unit. A value in your head earns nothing.
- Use the waiting. While flux cleaner dries or a program uploads, write the next heading of your report.
Checkpoints you can measure
A checkpoint is a clock time and a result you can show. "Power half done by 10:30" is not one. "10:30: 3.30 V at TP1, idle current under 15 mA" is.
Put three in a three-hour module, at about a quarter, half and three quarters of the time. Next to each, write what you will do if you are late. Decide it now, while you are calm. The lesson on time against marks shows how to choose what to cut.
The logbook
One line for each job, written when the job ends, not at the end of the day:
| Field | Example |
|---|---|
| Date | 2026-11-25 |
| Module and job | Sensor board: fit SOIC-8 and passives |
| Planned minutes | 45 |
| Real minutes | 58 |
| Difference | +13 |
| Cause code | F (a fault I made) |
| What happened | Bridge on U3 pins 6 and 7, 9 minutes to clear |
| One change | Flux the SOIC-8 pads first; fit it while my hands are fresh |
Our cause codes: P misread the task, T tool or part not ready, F a fault I made, K something I did not know, E equipment failure, N none, it simply took that long.
Once a week, sort the lines by difference. The top three show where your time goes. Fix their causes. "Be faster" is not a change. "Sort the parts into a labelled tray while I plan" is.
On the competition day
If you get time to try the equipment before the first module, spend it on the things your log says cost you minutes: the iron's real tip temperature, the scope's probe setting, the software versions on the PC, where the spare parts are kept. Write what you find on your plan sheet.
Worked example
Our practice module. Build and prove a 3.3 V sensor board in 180 minutes: fit 28 parts (one SOIC-8, the rest 0805 and through-hole), check the rail, program a sensor read, record three measurements, write one page. Start 09:00. This is an ARGYNIX practice task, not an official test project.
Step 1. Deliverables. Reading with a pen gave 19, from "D1 all 28 parts fitted" to "D19 bench cleared". Two questions went on the Expert list.
Step 2. Times from the log. The last ten times for "fit SOIC-8 and passives" were 41, 44, 40, 52, 45, 43, 47, 60, 42 and 46 minutes. Sorted, the eighth is 47. The best, 40, is not used.
Step 3. The plan.
| # | Job | 80% time | Start | Blocks |
|---|---|---|---|---|
| 1 | Read, list deliverables, plan, sort parts | 12 | 09:00 | everything |
| 2 | Fit the power block | 20 | 09:12 | 3 |
| 3 | Power test: rail and idle current | 8 | 09:32 | 4 |
| 4 | Fit SOIC-8, passives, headers | 47 | 09:40 | 5 |
| 5 | Inspect, clean | 10 | 10:27 | 6 |
| 6 | Program, read the sensor | 28 | 10:37 | 7 |
| 7 | Measurements into the table | 15 | 11:05 | 8 |
| 8 | Report page | 15 | 11:20 | |
| 9 | Buffer | 15 | 11:35 | |
| 10 | Final check of files, bench clean | 10 | 11:50 |
The total is 180 minutes. Checkpoints: CP1 09:40, 3.30 V ±2% at TP1 with idle current under 15 mA. CP2 10:37, board inspected, no rejects. CP3 11:20, three values in the table with units. Decision written beside CP2: "Late by more than 10 minutes: use the buffer, and write the report with only the items the task asks for."
Step 4. What happened.
| Job | Planned | Real | Cause |
|---|---|---|---|
| 1 | 12 | 10 | N |
| 2 | 20 | 24 | T: the 10 µF capacitor was in a mixed tray, 4 minutes to find |
| 3 | 8 | 6 | N |
| 4 | 47 | 58 | F: bridge on the SOIC-8 |
| 5 | 10 | 10 | N |
CP1 was on time: 09:40, 3.29 V at TP1, 11 mA. At CP2 the clock said 10:48, 11 minutes late. The decision was already written, so it took no thought: the buffer went, and the report kept only what the task asked for. The module finished at 11:57.
Step 5. The changes. Two causes, two changes: sort every part into a labelled tray during job 1, and flux the SOIC-8 pads before placing it. Until the bridges stop, the plan for job 4 uses the new data. Its 80% time is now 52 minutes.
Practice task
- Take a kit or an old practice board with 25 to 40 parts.
- In 10 minutes, write the deliverables list, numbered, with every value and its limit.
- Fill
module-plan-template.md: jobs, 80% times (or guesses, marked), start times, three checkpoints, and the decision beside each. - Work with a timer. Write each job's real time the moment it ends.
- Fill the log lines in
training-log.csv. Sort by difference. Choose one change. - Repeat with a different board next week. After four weeks, work out your 80% times again from the log.
Common mistakes
- Planning with your best time. Use the time you beat in 8 runs of 10.
- Checkpoints you cannot measure. "Half done" cannot be checked. A voltage at a test point can.
- Writing the log at the end of the day. You remember the last hour, not the first.
- "Slow" as a cause. Write what happened: the part you hunted for, the bridge, the menu you could not find.
- Hoping to catch up. When you are late at a checkpoint, use the decision you wrote. Hope is not a plan.
- No buffer. A plan that fills every minute is late at its first surprise.
- Fitting the chip before testing the supply. The order of jobs is part of the plan.
- Skipping the plan because the task looks easy. Easy tasks are where deliverables get missed.
Self-check
- Your last ten times for one job are 12, 13, 13, 14, 14, 15, 16, 17, 20 and 24 minutes. Which do you plan with, and why not 12?
- Why fit and test the power block before you fit the microcontroller?
- Rewrite "power half done by 10:30" as a checkpoint.
- At checkpoint 2 you are 17 minutes late, with 15 minutes of buffer left. What do you do, and when should you have decided it?
- A log line says "slow soldering". Why is it useless, and what would be better?
- The 80% times of your jobs add up to 200 minutes for a 180-minute module. What now?
Show answers
- 17 minutes: the eighth of the ten sorted times, so you finished within it in 8 runs of 10. Planning with 12, your best, makes you late in 9 runs of 10.
- Because a fault on the supply, such as a wrong regulator or a reversed capacitor, can damage the chip. Found before the chip is fitted, it costs minutes. Found after, it can cost the chip and the hour you spent fitting it.
- For example: "10:30: 3.30 V ±2% at TP1, idle current under 15 mA." It names a time, a place on the board, a value and a limit, so anyone can check it.
- Use the decision you wrote beside checkpoint 2 when you planned, such as: use the buffer and trim the report to what the task asks for. You should have decided it at the start, while calm, so that at the checkpoint you act in seconds instead of thinking under stress.
- It names no cause, so it suggests no change. Better: "Bridge on U3 pins 6 and 7, 9 minutes to clear. Next time: flux the pads first." Now you know what to practise.
- Decide before you start what you will not do, using marks per minute (see the lesson on time against marks). Starting with a plan that cannot fit means the cut will happen anyway, later and by accident, usually to the report and the final checks.
Downloads
- module-plan-template.md: our one-page plan: the deliverables list, the job table with 80% times and start times, three checkpoints with their decisions, and the hand-in check.
- training-log.csv: the logbook as a spreadsheet, with the cause codes and the worked example's rows. Sort it by the difference column once a week.
Practise in ARGYNIX Lab
Nothing in this lesson runs in ARGYNIX Lab: planning is done on paper, at the bench, with a timer. Practise it every week instead. Plan one practice build on the template, run it against the clock, log every job, and work out your 80% times again each month. Your plans are good when you reach most checkpoints within 5 minutes.